Street Maintenance Resurfacing Program

The Warrensburg Street Department would like to advise residents and visitors of the community that the 2015 Street Maintenance Resurfacing Program will begin Monday, July 13 and run through July 18, 2015, weather permitting. Roto-milling (removing old surface) of city streets is scheduled to commence on Monday, with the resurfacing being completed on Saturday.

Residents and businesses are being asked not to park vehicles on the affected streets 
Monday through Friday, July 13 through July 18, 2015, or until after the resurfacing process is completed.

No parking signs will be posted by the Street Department and vehicles may be towed at the owner’s expense. The streets scheduled for resurfacing are as follows in their 
approximate order of work:

Monday July 13: Ridgeview Dr. from Kimberly to Montserrat will be milled, followed with
the asphalt overlay on Tuesday, July 14.

Tuesday July 14: Summer Place & Parkway Dr. from Montserrat to Sunrise Dr. and 
Anderson St. from 9th St. to Broad will be milled, followed with the 
asphalt overlay on Wednesday, July 15.
.
Wednesday, July 15: Burkarth Rd. from Gay to Young and East Clark from Maguire to Zoll will be milled, followed with the asphalt overlay on 
Thursday, July 16.

Thursday, July 16: Hawthorne Hill, Circle Dr., and Woodland Trail in the Springridge Subdivision will be milled, follow by the asphalt overlay on 
Friday, July 17.

Saturday, July 18: South St. from Holden St. to Washington St. will be milled and asphalt overlayed.

The success and quality of the program depends on the support and cooperation of the public. 
Should area residents have questions concerning the program, please contact the Public Works Department at 747-9135.